CLIENT: SUBSEA 7
CONTRACT VALUE: £1.9m
Subsea 7 awarded Gow’s the contract to Manufacture, Test, and delivery to site the following Spacer Packages:
- 3260 Main Spacers
- 3308 Intermediate Spacers
- 48 Transition Spacers
- Pipe Spools to B31.3 ASME 9
Scope of Project
- Production of Project Preliminaries
- Procurement of Materials
- Preparation of test Jigs
- Manufacture templates & No go gauges
- Manufacture, setup, tack welding
- Welding activities
- Weld Inspection (MPI + Visual)
- Dimensional Inspection
- Fit Skid Blocks
- Fit Rollers, Apply Grease
- Carry out fabrication of pipe spools
- Weld Inspection (10{b855a61f1c31d0d7163aaa24d846501888ee2dceb50c234d7d40fc871f3dfdac} Radiography)
- Hydrostatic testing of spools using calibrated equipment
- Dimensional Inspection
- Final Inspection / Release
- Safe Packaging
- Transportation to Site
- Production of Lifetime Quality Records
Scope of Supply
- 3260 Main Spacers
- 3308 Intermediate Spacers
- 48 Transition Spacers
- Pipework Spools to B31.3 ASME 9
- All mechanical components were manufactured, tested and inspected at Gow’s Lybster Limited’s premises.
Industry Standards
- Fabrication & Welding to be in accordance with Norsok M-101
- All NDE to be in accordance with Norsok M101 Tables 5,6 & 7
- Welding Symbols to be in accordance with BS EN ISO 2553
- All protective coatings in accordance with Norsok M501 System 7B